Clark County permit timelines: median days to issue by type
How long do commercial permits take in Clark County? Median days from filing to issuance, by permit type, measured from 2456 issued permits.
| Permit type | Median days to issue | Sample |
|---|---|---|
| Commercial Electric | same day | n=1276 |
| Commercial Building Remodel/Repair | 50 days | n=627 |
| Commercial Building New | 62 days | n=406 |
| Commercial Demolition Permit | 24 days | n=108 |
| Commercial Building Addition | 101 days | n=39 |
Medians measured filing-to-issuance from timeline: bulk city records and dated status timelines. Cells publish at n>=30 issued permits.