Clark County permit timelines: median days to issue by type
How long do commercial permits take in Clark County? Median days from filing to issuance, by permit type, measured from 1598 issued permits.
| Permit type | Median days to issue | Sample |
|---|---|---|
| Commercial Electric | same day | n=844 |
| Commercial Building Remodel/Repair | 50 days | n=431 |
| Commercial Building New | 69 days | n=252 |
| Commercial Demolition Permit | 24 days | n=71 |
Medians measured filing-to-issuance from timeline: bulk city records and dated status timelines. Cells publish at n>=30 issued permits.