Denver permit timelines: median days to issue by type
How long do commercial permits take in Denver? Median days from filing to issuance, by permit type, measured from 131591 issued permits.
| Permit type | Median days to issue | Sample |
|---|---|---|
| Residential Construction Permit | 18 days | n=78851 |
| Commercial Construction Permit | 26 days | n=42804 |
| Demolition | 6 days | n=9685 |
| COMMERCIAL ALTERATION | 11 days | n=199 |
| COMMERCIAL SPECIAL EVENT | 2 days | n=52 |
Medians measured filing-to-issuance from timeline, history: bulk city records and dated status timelines. Cells publish at n>=30 issued permits.