San Antonio permit timelines: median days to issue by type
How long do commercial permits take in San Antonio? Median days from filing to issuance, by permit type, measured from 354299 issued permits.
| Permit type | Median days to issue | Sample |
|---|---|---|
| Mechanical Permit | same day | n=34504 |
| Plumbing General Permit | same day | n=31884 |
| Electrical General Permit | same day | n=29865 |
| Plumbing Irrigation Permit | same day | n=25438 |
| Res New Building Permit | 12 days | n=20282 |
| Re-Roof Permit | same day | n=18739 |
| MEP Trade Permits Application | same day | n=18726 |
| Residential Repair Permit | 1 day | n=18373 |
| Solar - Photovoltaic Permit | 5 days | n=14220 |
| Garage Sale | same day | n=12709 |
| Foundation Repair Permit | 1 day | n=12653 |
| LSR Plumbing Permit | same day | n=11498 |
| Plumbing Gas Permit | same day | n=10184 |
| Plumbing Sewer Permit | same day | n=9414 |
| LSR Mechanical Permit | same day | n=8608 |
| On Premise Sign | 8 days | n=7688 |
| Minor Building Repair | same day | n=6775 |
| Tree Affidavit Permit | 18 days | n=6714 |
| Residential Fence Permit | same day | n=5333 |
| Sidewalk-Curb Permit | 1 day | n=4586 |
| Electrical TOPS Permit | same day | n=3320 |
| Across the Street Banner | same day | n=2946 |
| Home Addition Permit | same day | n=2552 |
| Swimming Pool or Spa Permit | 2 days | n=2258 |
| Minor Commercial Repair Permit | 1 day | n=2163 |
| Plumbing Backflow Permit | same day | n=2070 |
| Tree Permit | 42 days | n=2014 |
| Demolition Permit | 35 days | n=1895 |
| Res Building Application | 7 days | n=1879 |
| LSR MEP Permit Application | same day | n=1792 |
| Electrical TML Permit | same day | n=1585 |
| Maintenance Permit | same day | n=1562 |
| Covered Patio or Porch Permit | same day | n=1353 |
| Tree Application | 18 days | n=1265 |
| Carport Permit | same day | n=1186 |
| Comm Remodel Permit | 46 days | n=1178 |
| Comm New Building Permit | 98 days | n=1169 |
| Sign Permit Application | 11 days | n=1124 |
| Comm Comm Equipment Permit | 13 days | n=928 |
| Electrical Completion Permit | 1 day | n=875 |
+35 more permit types tracked
Medians measured filing-to-issuance from history: bulk city records and dated status timelines. Cells publish at n>=30 issued permits.