Tampa permit timelines: median days to issue by type
How long do commercial permits take in Tampa? Median days from filing to issuance, by permit type, measured from 658 issued permits.
| Permit type | Median days to issue | Sample |
|---|---|---|
| Commercial Mechanical Trade Permit | same day | n=371 |
| Commercial Plumbing Trade Permit | same day | n=101 |
| Commercial Electrical Trade Permit | same day | n=89 |
| Commercial Building Trade Permit | same day | n=49 |
| Commercial Building Alterations (Renovations) | 30 days | n=48 |
Medians measured filing-to-issuance from timeline: bulk city records and dated status timelines. Cells publish at n>=30 issued permits.