Tampa, FL

Tampa permit timelines: median days to issue by type

How long do commercial permits take in Tampa? Median days from filing to issuance, by permit type, measured from 658 issued permits.

Permit typeMedian days to issueSample
Commercial Mechanical Trade Permitsame dayn=371
Commercial Plumbing Trade Permitsame dayn=101
Commercial Electrical Trade Permitsame dayn=89
Commercial Building Trade Permitsame dayn=49
Commercial Building Alterations (Renovations)30 daysn=48

Medians measured filing-to-issuance from timeline: bulk city records and dated status timelines. Cells publish at n>=30 issued permits.